Railway Completes Safety Trials and Inspection of Tihi-Dhar Rail Section
Dhar, November 16, 2026 (Udaipur Kiran): Railways has completed multiple trials and safety inspections on the newly constructed Tihi-Dhar railway section following the completion of the tunnel construction.
The first tower wagon trial on this section was conducted on October 26. Over the next eight days, Railways carried out trials between Tihi and Dhar in different phases. Initially, a diesel locomotive was used, followed by an electric locomotive.

Track Tested at Speeds of Up to 130 kmph
During the trials, railway officials closely examined bridges, tracks, overhead equipment (OHE), the signalling system and other safety arrangements along the newly constructed railway line.
After these tests, a speed trial was also conducted at 130 kmph to assess the section’s performance.
Commissioner of Railway Safety Inspects Section
After completion of the trial process, E. Srinivas, Commissioner of Railway Safety for the Western Circle, inspected the railway section on November 5 and 6.
On the first day, he inspected the section from Tihi to Gunawad using a trolley. On the second day, the inspection covered the Gunawad-Dhar section.
The inspection included bridges, railway tracks, signalling systems, overhead equipment and facilities inside the approximately three-kilometre-long Tihi Tunnel.
On November 6, a speed inspection was also conducted using a special inspection vehicle.