Udaipur, November 16, 2026 (Udaipur Kiran): The long-pending plan to connect Mewar and Marwar directly through a broad-gauge railway line has once again hit a roadblock due to the lack of forest department clearance. The Railway Board approved a budget of ₹11.75 crore for surveying a proposed 93.1-km railway route between Marwar Junction and Devgarh Madariya via Siriyari. However, the survey has not started even after a year because the Forest Department has not issued the required No Objection Certificate (NOC).

The Railway Board has written to the Forest Department seeking approval, but the project is still awaiting clearance.

Meanwhile, broad-gauge work between Nathdwara and Devgarh Madariya is underway, with completion targeted for 2027. The delay in planning the onward connection to Marwar has raised concerns that the railway line being built at a cost of crores could end up at Devgarh without fulfilling its original objective of connecting Mewar and Marwar.

Mewar-Marwar Rail Link Stuck Over Forest Clearance

Direct Rail Connectivity Between Udaipur, Rajsamand and Pali at Stake

The proposed railway link is expected to establish direct rail connectivity between Udaipur, Rajsamand and Pali, along with other areas of Marwar. It would also make travel to Jodhpur and surrounding areas easier.

If the route is not surveyed and approved in time, the broader plan to connect the railway networks of Mewar and Marwar could remain incomplete.

Tourism and Industries Expected to Benefit

The proposed railway line is expected to offer several benefits:

  • Direct connectivity: Udaipur, Rajsamand, Pali and other parts of Marwar would get a direct connection with the Mewar railway network.
  • Tourism growth: Travel between Udaipur, Chittorgarh, Goram Ghat and historical and religious destinations in Marwar could become easier for tourists and devotees.
  • New markets for industries: Kishangarh’s marble industry, Jodhpur’s handicrafts and stone industry, Kankroli’s tyre industry, and Pali’s textile, henna and lime industries could gain additional transportation options.
  • Business and employment: Better rail connectivity could support trade and create new employment opportunities.

Tunnels and 5 to 7 New Stations Proposed

The Railway Board approved ₹11.75 crore for a fresh survey of the project after a gap of around nine years. North Western Railway is responsible for conducting the survey.

Instead of taking the route from Devgarh Madariya towards Khamli Ghat and Goram Ghat, the latest proposal is to connect the line to Phulad through Todgarh and Siriyari.

The proposed route would pass through hilly and forest areas, where tunnels may be constructed to carry the railway line. Between five and seven new railway stations are also proposed, including stations at Siriyari and Todgarh.

However, the process remains stalled because the necessary permissions for the forest areas have not been granted.

Three Surveys Conducted for the Mewar-Marwar Rail Link

Railways has conducted three surveys so far to explore a direct railway connection between Mewar and Marwar.

First survey in 2007-08: The first survey covered a proposed 158-km route from Marwar Junction to Devgarh Madariya via Phulad, Goram Ghat and Khamli Ghat. A budget of ₹10.30 crore was approved for the survey.

Second survey in 2016-17: A 93.1-km route was surveyed, proposing a connection through Phulad, Siriyari, Borimadho, Bhavan, Bhujrail, Mandavan and Khamli Ghat to Devgarh Madariya. However, several sections of the proposed route fell within a wildlife sanctuary area, and the Forest Department did not grant clearance.

Third survey in 2021: Following discussions with Railway Minister Ashwini Vaishnaw, an alternative route of 108 km was surveyed. It proposed connecting Devgarh Madariya with Haripur through Lasani, Tal, Bhim, Bali, Jawaja and Bar.

The report submitted by North Western Railway has remained pending for the past three years, awaiting approval from the Cabinet Committee on Economic Affairs and budget allocation.

Expert Suggests Tunnels and Elevated Tracks

Prakash Mandot, president of the Mewar Rail Development Council, said that environmental regulations must be followed to construct a railway line through the Rawli-Todgarh Wildlife Sanctuary area.

He suggested that technical solutions such as elevated tracks, underpasses and long tunnels could be considered while ensuring that the natural corridors used by wildlife remain protected.

Frequently Asked Questions

1. Why is the Mewar-Marwar railway project delayed?

The proposed railway survey has not started because the Forest Department has not issued the required No Objection Certificate.

2. How much budget has the Railway Board approved for the latest survey?

The Railway Board has approved ₹11.75 crore for surveying the proposed 93.1-km route.

3. Which route is proposed in the latest survey?

The proposed route will connect Marwar Junction with Devgarh Madariya through Siriyari, with the line planned to pass through Todgarh and reach Phulad.

4. How long is the proposed Marwar Junction-Devgarh Madariya route?

The latest proposed route is 93.1 km long.

5. When is the Nathdwara-Devgarh Madariya broad-gauge project expected to be completed?

The work is underway, and the target for completion is 2027.

6. How many surveys have been conducted for the Mewar-Marwar rail link?

Railways has conducted three surveys: in 2007-08, 2016-17 and 2021.

7. Which industries could benefit from the proposed railway connection?

Kishangarh’s marble industry, Jodhpur’s handicrafts and stone industry, Kankroli’s tyre industry, and Pali’s textile, henna and lime industries are expected to benefit.

8. What alternatives have been suggested to protect the wildlife sanctuary?

Elevated tracks, underpasses and long tunnels have been suggested as possible options to protect natural wildlife corridors while developing the railway route.